Protect the carrier cutoff
Directional decision file for a 4,800 m² distribution centre testing whether layout and dispatch changes can clear a 28% peak-volume uplift without a night shift.
Decision at a glance
The baseline fails the 3:00 pm carrier cutoff. A shorter dispatch path plus one additional marshalling zone clears the modelled peak without adding a night shift.
Spatial bottleneck
Dispatch work crosses the replenishment path, creating recurring interference immediately before the carrier cutoff.
Pick completion and replenishment traffic converge on one aisle.
Completed orders wait in the packing footprint instead of a dedicated dispatch zone.
The final dispatch wave exceeds the single-door clearing rate.
Scenario comparison
Each intervention is tested against the same demand profile, staffing and equipment uptime.
Evidence and confidence
This example shows how measured facts, supplied evidence, assumptions and unknowns are separated.
What is supported
- The baseline constraint occurs after packing
- Route shortening materially improves cycle time
- Marshalling capacity is required to reach the target
What remains unknown
- Final fire-egress and safety clearance
- Structural and services implications
- November demand volatility outside the supplied range